Commercial Case Study / 2022
Finishing carpentry for Vancouver's tallest tower in our portfolio
Right Group Construction delivered the full interior finishing carpentry package across 444 suites and 56 storeys at One Burrard Place, turning over floors on the general contractor's schedule with a fixed unit standard.
1289 Hornby St, Vancouver, BC · Developer: Reliance Holdings / Jim Pattison Developments
444
Units Finished
56
Storeys
100%
Turnovers On Schedule
01 / The Challenge
A 56-storey concrete tower gives a finishing trade almost no float. Material had to reach the right floor at the right time using shared hoists, and every suite had to read identically whether it was on level 6 or level 54 — with the GC's turnover sequence moving faster than a typical mid-rise.
Scope Delivered
- Suite and closet door hanging
- MDF casing and baseboard packages
- Locksets, closers and soft-close hardware
- FJP and MDF window sills
- Washroom accessories and blocking
- Per-unit deficiency close-out
02 / Our Approach
Floor-by-floor staging plan
We agreed hoist windows and staging locations before mobilization, so doors, casing and hardware landed on the working floor the day crews needed them — not three floors down.
One fixed unit standard
Reveals, casing returns, base mitres and hardware heights were locked to a written standard on the mock-up suite, then repeated on all 444 units so QC was a check, not a negotiation.
QC walk before every turnover
Our site supervisor walked every suite against a checklist before it left our scope, closing deficiencies internally instead of pushing them onto the GC's list.


03 / The Outcome
- 444 suites finished and turned over without a schedule extension request from our scope.
- Deficiency counts stayed low enough to be closed within the same floor cycle.
- All extras confirmed in writing before execution — no disputed change orders at close-out.
Frequently asked
How many units can Right Group finish per week on a high-rise?+
Do you work labour-only on towers?+
More commercial case studies
Gateway Residences — Two Towers, 298 Units
Right Group Construction completed the finishing carpentry scope for 298 units across two towers at Gateway Residences in West Vancouver, coordinating both buildings against a single shared logistics plan over a three-level parkade.
Timothy Hall, UBC — 50,293 sq ft Institutional Build
Right Group Construction delivered the finishing carpentry scope for Timothy Hall at UBC — a 50,293 square foot institutional building — meeting campus access rules, hollow metal door specifications and accessibility hardware requirements.